Recent Projects
01
Project: Six Sewer Transfer
Owner: Costa Mesa Sanitation Distrct
Contract amount: $650,000
Completed Jan 2012
TTS was contracted to remove and install 600 l/f of 10 SDR26 sewer system and repave 660 l/f of the east bound lanes on South Coast drive between harbor and Fairview in the city of Costa Mesa . The work was completed at night due to the traffic impact of the construction. The Job was very challenging from the start, TTS had to install a sewer bypass to keep the existing sewer flowing while removing and replacing the new line. TTS was challenged with the soils, ground water and depth which complicated the process to get the job done within budget. TTS and CMSD re engineered the trench to protect the safety of the public and TTS crews. TTS pushed thru the job while only installing an average of 25 l/f a night. Between the hard work and dedication of the team the job was completed under the time frame given by CMSD .
Project: Pacific Arts Plaza, Costa Mesa
Owner: Irvine Company
Contractor: Cuesta Construction
Contracted amount: 1.55 million
Completed Dec 2011
Pacific arts plaza was a site redevelopment of approx. 2.5 acres right in the heart of the orange countys center of business and across the street from South coast plaza. The work encompassed working within 4 high rise buildings and open business complex while maintaining flow to all tenants, traffic and accessibility. TTS was contracted for the wet utilitys, grading, paving for the project. TTS scope included to demo and remove an existing 17,000 sq, ft foundation buried below grade, prepare a 40,000 sq. ft. pad for a new parking structure, grade and base 140,000 sq. ft of new paving, concrete and landscaping per the new design, relocate all underground utilitys and install all new storm drain system. TTS paved approx. 95,000 sq. ft of new asphalt. The schedule was demanding and required TTS to work 7 days a week 10 hours a day for 6 weeks to complete the project within time for the owner and at the same time not compromise safety and quality.
02
03
Project: Walnut Drainage
Owner: City of Costa Mesa
Contractor: TTS Engineering Inc.
Contracted amount: $585,000
Completed: Jan 2011
TTS Engineering was the response low bidder for the City of Costa Mesa. TTS was awarded the job and contracted to install 500 l/f of new 60 RCP on walnut drive,. TTS performed all the concrete structures, Manholes and catch basins in house. TTS was contracted to replace all the site concrete associated with the construction. TTS Was contracted to grind and replace approx. 22,000 sq. ft of of street after construction. TTS crews work within the residencial streets while leaving access open to all the home owners. The clanging portion of the project was the relocation of all the existing utilities while keeping all the homeowners out of service. The contract was completed on time and within budget for the City of Costa Mesa.